Time Line
| 2007 | 2008 | 2009 | ||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Task Name | Starts | Finish | Duration | Assigned | Dec | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan |
| Board Approval | 11/29/07 | 11/29/07 | 1 Day | VC of IT | ||||||||||||||
| Fit and Gap Analysis Phase | 01/02/08 | 03/07/08 | 66 Days | AD SA | ||||||||||||||
| Development Phase | 03/17/08 | 06/14/08 | 90 Days | AD SA | ||||||||||||||
| Transition Phase | 05/19/08 | 10/10/08 | 145 Days | |||||||||||||||
| System Testing | 05/19/08 | 06/13/08 | 26 Days | AD SA SMEs | ||||||||||||||
| Integration Testing | 06/16/08 | 07/11/08 | 26 Days | AD SA SMEs | ||||||||||||||
| Parallel Testing | 07/14/08 | 08/29/08 | 47 Days | AD SA SMEs | ||||||||||||||
| Life Cycle Testing | 09/02/08 | 10/03/08 | 32 Days | AD SA SMEs | ||||||||||||||
| User Acceptance Testing | 10/06/08 | 10/10/08 | 5 Days | AD SA SMEs | ||||||||||||||
| Training (Train the Trainer) | 07/21/08 | 11/30/08 | 133 Days | AD SA/Upgrade Partner/ELOD | ||||||||||||||
| Deployment | 10/27/08 | 01/31/09 | 97 Days | |||||||||||||||
| Prepare Production Rollout | 10/27/08 | 10/29/08 | 3 Days | All | ||||||||||||||
| Convert database to v9 | 10/30/08 | 11/02/08 | 4 Days | All | ||||||||||||||
| Go Live | 11/03/08 | 11/03/08 | 1 Day | All | |
|||||||||||||
| Post Go Live Support | 11/04/08 | 01/31/09 | 89 Days | All | ||||||||||||||