Time Line

          2007 2008 2009
Task Name Starts Finish Duration Assigned Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Board Approval 11/29/07 11/29/07 1 Day VC of IT
scale
                         
Fit and Gap Analysis Phase 01/02/08 03/07/08 66 Days AD SA   scale scale scale                    
Development Phase 03/17/08 06/14/08 90 Days AD SA    
scale
scale scale scale scale              
Transition Phase 05/19/08 10/10/08 145 Days            
scale
scale scale scale scale scale      
System Testing 05/19/08 06/13/08 26 Days AD SA SMEs          
scale
scale              
Integration Testing 06/16/08 07/11/08 26 Days AD SA SMEs            
scale
scale            
Parallel Testing 07/14/08 08/29/08 47 Days AD SA SMEs              
scale
scale          
Life Cycle Testing 09/02/08 10/03/08 32 Days AD SA SMEs                  
scale
scale      
User Acceptance Testing 10/06/08 10/10/08 5 Days AD SA SMEs                    
scale
     
Training (Train the Trainer) 07/21/08 11/30/08 133 Days AD SA/Upgrade Partner/ELOD              
scale
scale scale scale      
Deployment 10/27/08 01/31/09 97 Days                      
scale
scale scale scale
Prepare Production Rollout 10/27/08 10/29/08 3 Days All                    
scale 
     
Convert database to v9 10/30/08 11/02/08 4 Days All                    
scale
scale    
Go Live 11/03/08 11/03/08 1 Day All                        scale    
Post Go Live Support 11/04/08 01/31/09 89 Days All